LEAKESVILLE PROJECTS AND GRANTS
• Boat Ramp Improvements (H) o April 2023: Application Process o July 2023: Awarded Grant for $53,000 (75% of project cost) o August 1st 2023: Ground Breaking o August 15th, 2023: Project Completed.
​
• AFG (Assistance to Firefighters Grant: FEMA) (H) o January 2024: Pre-Application begins o March 8th, 2024: Application submitted for $75,000.
• Jernigan Rd Extension - $1,826,424.00 (100%, Local waved) o April, 2022: Begin exploring funding sources to extend waterline down Jernigan Rd o August 2022: Approve application o October 2022: Notice of Appropriations Committee Approval o April 26th, 2023: Notice of Award o May 2023: NEPA Study Required o October 2023: Professional Engineering Services Proposals Accepted o June 13, 2024: NEPA Study Completed, Preliminary Engineering Report Completed
• HSG (MS Homeland Security Grant) (H) o March 2024: Pre-application o April 1st, 2024: Grant Submission o July 9th, 2024: Grant awarded: $10,756.00 for two LPR Cameras o August 7th, 2024: Grant Orientation o September 1st: Purchases begin for grant
• Firehouse Subs(H) – 6 SCBA’s and setups P a g e 2 | 3 LEAKESVILLE PROJECTS AND GRANTS o June 24th, 2024: Pre-application o July 11th, 2024: Application submitted o July 12th, 2024: Applications exceeded available slots.
• State Farm Grant (H)– 4 SCBA’s and setups o July 25th , 2024: Pre-application o August 1st, 2024: Application Submitted
​
• Various Infrastructure. State Appropriation Request. o December 2022: Pre-Legislative meeting to discuss upcoming 2023 Session requests.
â–ª Various streets in critical need. Storm water upgrades. Roadwork equipment. Chickasawhay Bridge (old) upgrades to open to public. Annex Road upgrades. Hurricane Debris Clean up
â–ª Total Request. $1,239,565.05
â–ª January 5th, 2023: Letters submitted to Senator Debar, Rep. Dale Goodin â–ª April 2023: Sine Die. No assistance awarded o December 2023: Pre-Legislative meeting to discuss upcoming 2024 Session requests.
â–ª Various streets in critical need. Storm water upgrades. Roadwork equipment. Chickasawhay Bridge (old) upgrades to open to public. Annex Road upgrades. Money for aprons on either side of Bear Creek’s new bridge. Matching funds for MDOT grant. Increased spending at Boat Ramp for bank stabilization. Hurricane Zeta Debris Clean up.
â–ª Total Request: $1,514,585.05 â–ª February 27th, 2024: Submitted letters to Senator Debar and Rep. Elliot Burch â–ª April 2024: Sine Die. No assistance awarded.
• River Street Revitalization o Phase 1: Boat Ramp Improvements. Completed August 2023 o Phase 2: New Surface for River Street itself – August 2023 P a g e 3 | 3 LEAKESVILLE PROJECTS AND GRANTS o August 14, 2024: Letter sent to Senator Hyde-Smith requesting assistance in reopening the old bridge for pedestrian traffic. o Phase 3: Long term lease for additional parking on shoulder of River Street near boat ramp.
• Lafayette Ave Emergency Repairs - $324, 879.28 o July 1st ,2022: Hole detected in surface of Lafayette Ave roadway. After investigation it was determined that the culverts had separated and had washed most of the material holding up the surface of the road. Engineers contacted. o July 5th, 2022: Board declares a state of emergency and closes the roadway. o July 6th, 2022: Work begins on drafting a response plan to fix issue. o August 12th, 2022: Engineers submit preliminary engineering plans o August-October 13th: Engineering plans are updated more than 8 times. Advertisement for bids for project submitted. o January 2023: Phase 1 begins. Removal of old culverts and materials. o February 2023: Phase 2 begins. Installation of headwalls and bulkheads o March 2023: Installation of culverts, backfill materials. Rough roadbed. Ditches on both sides of road are lined with concrete to avoid future problems. o April 2023: Final layers of asphalt put into place. Bridge Reopened.
• Gallows Branch Bridge Rehabilitation Emergency - $58,200 o September 2022: Inspection of bridge indicates imminent failure o September 15th, 2022: Board declares a state of emergency for Gallows Branch Bridge. o October 2022: Specialist brought in to replace and repair bridge pilings and headwalls. Surface of bridge removed back to original bridge decking. o January 2023: Final surface added to bridge.